Acceptance Testing a Robot Cell: The Plan to Write First

Published: Publisher: Zhilianhai Robotics News

Two tests, two places

TestWherePurpose
Factory acceptance (FAT)At the integratorProve the cell works before shipping
Site acceptance (SAT)At your plantProve it works with your parts, people and power

Make the criteria numeric

“Works well” is not a criterion. Write the sample size, the acceptable cycle time range, the allowed intervention rate and the duration of the run. For example: 500 parts, cycle time within 5% of the agreed figure, no more than 2 manual interventions, safety functions verified against the risk assessment.

Test the failure paths

  • Stop and restart at every point in the cycle.
  • E-stop from each operator position, timed and recorded.
  • Power loss during a move, then recovery.
  • Bad part, missing part, upside-down part.
  • Network drop between robot and line controller.

Record each test with a date, the person who ran it and the result. That record is what the maintenance team will use for years.

This article is published by the Zhilianhai Robotics News site. Where policies, standards, prices, company capabilities or project status are involved, cross-check the original sources as well.

Back to section

Company information

Company information in this section comes from the Zhilianhai company database. To add or correct company data, go to Company Directory to look up the company, or submit a data verification request via Contact Us; once the company data upload channel opens, this module will handle it.

Latest materials in this section

Discussion and comments

CONTACT US

公司:Zhilianhai Robotics Intelligence

地址:Nanshan District, Shenzhen, Guangdong, China

Q Q:

Copyright © 2026 Zhilianhai Robotics Intelligence

Robotics enquiries