Acceptance Criteria in the RFQ, Not in the Contract

Published: Publisher: Zhilianhai Robotics News

What to define early

  • Sample size for the cycle-time test.
  • How the cycle time is measured: from which signal to which signal.
  • The permitted number of manual interventions per shift.
  • Which safety functions are tested, and who witnesses them.

Why it belongs in the RFQ

If acceptance is defined after award, the vendor has already priced an assumption. Writing it in the RFQ means every bidder prices the same obligation, and it removes the single most common source of disputes.

This article is published by the Zhilianhai Robotics News site. Where policies, standards, prices, company capabilities or project status are involved, cross-check the original sources as well.

Back to section

Company information

Company information in this section comes from the Zhilianhai company database. To add or correct company data, go to Company Directory to look up the company, or submit a data verification request via Contact Us; once the company data upload channel opens, this module will handle it.

Latest materials in this section

Discussion and comments