Payment Milestones in Robotics Contracts

Published: Publisher: Zhilianhai Robotics News

A workable milestone pattern

MilestoneTypical share
Contract signature20 to 30 per cent
Design freeze and long-lead order20 to 30 per cent
Factory acceptance test20 to 30 per cent
Installation complete10 to 20 per cent
Site acceptance and handover10 to 20 per cent
Retention after warranty5 to 10 per cent

Protect both sides

  • Tie each payment to an observable, testable event.
  • Define what happens if a milestone slips.
  • Agree the retention period and release conditions in advance.
  • Keep variation orders inside the same payment structure.

Payment terms vary by market and supplier. Take local legal advice for large contracts.

This article is published by the Zhilianhai Robotics News site. Where policies, standards, prices, company capabilities or project status are involved, cross-check the original sources as well.

Back to section

Company information

Company information in this section comes from the Zhilianhai company database. To add or correct company data, go to Company Directory to look up the company, or submit a data verification request via Contact Us; once the company data upload channel opens, this module will handle it.

Latest materials in this section

Discussion and comments