Cycle Time Estimation for Robot Cells

Published: Publisher: Zhilianhai Robotics News

Build the estimate in layers

LayerWhat to include
MotionRobot travel at realistic speeds and accelerations
GrippingClosing, confirming and releasing
SensingImage capture, processing and handshakes
ProcessWelding, grinding, dispensing or curing time
WaitingConveyor indexing, door opening and interlock handshakes
RecoveryRework, purging and part rejection

Rules of thumb

  • Add 15 to 30 per cent contingency on top of the calculated cycle.
  • Measure a comparable manual or automated station before committing.
  • Account for start-up and changeover losses, not only steady state.
  • Model the slowest station rather than the average.

Simulation and vendor figures are estimates. Validate on the real cell before accepting a capacity commitment.

This article is published by the Zhilianhai Robotics News site. Where policies, standards, prices, company capabilities or project status are involved, cross-check the original sources as well.

Back to section

Company information

Company information in this section comes from the Zhilianhai company database. To add or correct company data, go to Company Directory to look up the company, or submit a data verification request via Contact Us; once the company data upload channel opens, this module will handle it.

Latest materials in this section

Discussion and comments