Site Readiness Checklist Before Delivery
Most delays at installation are site problems, not robot problems.
Before the equipment arrives
| Item | Check |
|---|---|
| Power | Capacity, isolation point and protection installed |
| Air | Pressure, flow and quality verified |
| Floor | Level, load capacity and fixing method confirmed |
| Access | Route, door widths and lifting equipment arranged |
| Environment | Dust, temperature and humidity within specification |
| People | Operators and maintenance staff available for training |
How to use the checklist
- Walk the checklist with the integrator a month before delivery.
- Photograph any deviation and agree the remedy and owner.
- Do not accept delivery into an unfinished area unless unboxing is agreed.
Site readiness requirements come from the equipment documentation. Confirm them with the supplier.