Running a Robot Cell Acceptance Test

Published: Publisher: Zhilianhai Robotics News

What the test should cover

AreaWhat to verify
FunctionEvery operating mode and recovery routine
Cycle timeMeasured over a sustained run
QualityFirst pass yield at the agreed sample size
SafetyStops, interlocks and guards verified and recorded
DocumentsPrograms, parameters, spares list and training
TrainingOperators and maintenance staff competent to run it

How to run it

  • Agree the test plan and pass criteria before the equipment arrives.
  • Record the data and keep signed copies.
  • List every open defect with an owner and a date.

Acceptance criteria should be in the contract so both sides test against the same measures.

This article is published by the Zhilianhai Robotics News site. Where policies, standards, prices, company capabilities or project status are involved, cross-check the original sources as well.

Back to section

Company information

Company information in this section comes from the Zhilianhai company database. To add or correct company data, go to Company Directory to look up the company, or submit a data verification request via Contact Us; once the company data upload channel opens, this module will handle it.

Latest materials in this section

Discussion and comments